acf domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/iteclbco/projects.automationmate.com/wp-includes/functions.php on line 6170updraftplus domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/iteclbco/projects.automationmate.com/wp-includes/functions.php on line 6170wordpress-seo domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/iteclbco/projects.automationmate.com/wp-includes/functions.php on line 6170The post Qatar Gas – Package unit control system appeared first on Automate.
]]>
•Software development and graphics development for the control panel and operator unit.
•Control and monitor the two package units with field devices.
•Control programming and graphics development as per Qatar GAS standard.
•Integration of fire alarm and DCS systems via hard wiring for control system monitoring.
•Training for Qatar GAS maintenance team.
BENEFITS FOR THE CUSTOMER:
•Package Unit and 3rd party systems monitored and controlled by operator unit so the control can be done from one place.
•Efficient maintenance and troubleshooting because all the alarms are configured in the operator unit.
•Reduction of operational costs by identifying the errors and fault functions whenever occurring.
•Better control of internal comfort conditions and monitoring all risks.
•Less Manpower requirement to maintain the system.
•Less maintenance cost since Siemens products are more reliable in comparison with other brands.
IMPLEMENTATION:
•Programming the DDC controller as per Qatar GAS standards and requirements.
•Supervision of the sensor installation and cabling.
•Panel testing and commissioning and graphics development for operator unit.
•Panel FAT & SAT with Qatar GAS team.
•Fire integration and testing with fire alarm system.
•Training for Qatar GAS maintenance team.
For any inquiry or support, please contact us at support@automationmate.com
The post Qatar Gas – Package unit control system appeared first on Automate.
]]>The post Power Plant Scada System appeared first on Automate.
]]>•Full SCADA renovation for the Power Plant, replacing the old system and including new features.
•To supply and commission the new system.
•Replacement of old S7-400 PLC with new S7-400H, Redundant.
BENEFIT OF THE CUSTOMER:
•Siemens automation system used was based on Simatic S7-400H, Which will eliminate shut downtime and provide high availability.
•Individual computers were used, with the new system the database is centralized.
•It is possible to reduce operational costs, as the system is fully automated and doesn’t require any personal intervention, reports are generated automatically.
•It is possible to reduce maintenance costs, by using the highest product quality, fault detection, and event logging that allows tracing problems causes. Most of the analog signals are archived.
IMPLEMENTATION:
•To deliver a full control and monitoring system.
•Continuous Support and availability guaranteed know-how to be provided by the SP.
Product Quality, full integration, easy to configure.
For any inquiry or support, please contact us at support@automationmate.com
The post Power Plant Scada System appeared first on Automate.
]]>The post Masdar Solar Platform Lift Renovation appeared first on Automate.
]]>• Repair the Solar Lift that was operating with Mitsubishi Controller
• Replace the old Defected Mitsubishi PLC with a new Siemens Controller
• Reprogram the new controller and implement the same functionality
IMPLEMENTATION BY THE SOLUTION PARTNER :
• ET200SP CPU with NPN IOs
• Installing the best quality-price solution is a benet of the solution partner’s experience
• Having the same quality and satisfaction for the supplier
• Siemens was chose Based on the Client Requirements and the flexibility of the product range
• Step7 Professional V13 WinCC Runtime Professional V13
BENEFITS OF THE CUSTOMER :
• Latest Technology used, High availability of Spare Parts,
• Operation Costs Reduced due to the operator Station installed, all lift functionalities can be controlled from the operator workstation
• Monitor all System Inputs and Outputs Electrically for the operator PC installed in the control room
• Reprogram the new controller and implement the same functionality.